While working 7 hour a day, A alone can complete a piece of work in 6 days and B alone in 8 days. In what time would they complete it together, 8 hour a day?

  • 13 days
  • 24 days
  • 32.1 days
  • 43.6 days
Answer:- 1
Explanation:-

Solution:
A can complete the work in 7 × 6 = 42 hours
1 hour's work of A =
142

B can complete the work in 7 × 8 = 56 hours
1 hour's work of B =
156

(A + B)'s 1 hour's work
=142+156=4+3168=7168

∴ Time taken by (A + B) working 8 hours daily
1687×8=3days

Post your Comments

Your comments will be displayed only after manual approval.


B can complete the work in 7 × 8 = 56 hours
1 hour's work of B =
156

(A + B)'s 1 hour's work
=142+156=4+3168=7168

∴ Time taken by (A + B) working 8 hours daily
1687×8=3days

", "dateCreated": "7/24/2019 10:09:12 AM", "author": { "@type": "Person", "name": "Nitin Sir" } }, "suggestedAnswer": { "@type": "Answer", "text": "
Solution:
A can complete the work in 7 × 6 = 42 hours
1 hour's work of A =
142

B can complete the work in 7 × 8 = 56 hours
1 hour's work of B =
156

(A + B)'s 1 hour's work
=142+156=4+3168=7168

∴ Time taken by (A + B) working 8 hours daily
1687×8=3days

", "dateCreated": "7/24/2019 10:09:12 AM" } }
Test
Classes
E-Book