An engineer undertakes a project to build a road 15 km long in 300 days and employs 45 men for the purpose. After 100 days, he finds 2.5 km of the road has been completed. Find the (approx.) number of extra men he must employ to finish the work in time.

  • 143
  • 245
  • 355
  • 468
Answer:- 1
Explanation:-

Solution:
Variation Method:
In 100 days only 2.5 km rod i.e. 16.66 % of work has been completed
Men Days Road (km)
45 100 ↓ 2.5
X ↑ 200 12.5↑
Arrows show the directions of variation of quantity with respect to each other
x45=100×12.5200×2.5

x = 113 men;
Required men to be increased,
= 113 - 45 = 68

Post your Comments

Your comments will be displayed only after manual approval.


x = 113 men;
Required men to be increased,
= 113 - 45 = 68 ", "dateCreated": "7/24/2019 10:09:12 AM", "author": { "@type": "Person", "name": "Nitin Sir" } }, "suggestedAnswer": { "@type": "Answer", "text": "
Solution:
Variation Method:
In 100 days only 2.5 km rod i.e. 16.66 % of work has been completed
Men Days Road (km)
45 100 ↓ 2.5
X ↑ 200 12.5↑
Arrows show the directions of variation of quantity with respect to each other
x45=100×12.5200×2.5

x = 113 men;
Required men to be increased,
= 113 - 45 = 68 ", "dateCreated": "7/24/2019 10:09:12 AM" } }