Raj can do a piece of work in 20 days. He started the work and left after some days, when 25% work was done. After it Abhijit joined and completed it working for 10 days. In how many days Raj and Abhijit can do the complete work, working together?

  • 16
  • 28
  • 310
  • 412
Answer:- 1
Explanation:-

Solution:
Efficiency of Raj =
10020
= 5%
Work completed by Raj = 25%
Rest work = 75%
Efficiency of Abhijit =
7510
= 7.5%
Combined efficiency = 5 + 7.5 = 12.5%
They will complete the whole work by working together in,
=
10012.5
= 8 days

Post your Comments

Your comments will be displayed only after manual approval.

= 5%
Work completed by Raj = 25%
Rest work = 75%
Efficiency of Abhijit =
7510
= 7.5%
Combined efficiency = 5 + 7.5 = 12.5%
They will complete the whole work by working together in,
=
10012.5
= 8 days ", "dateCreated": "7/24/2019 10:09:12 AM", "author": { "@type": "Person", "name": "Nitin Sir" } }, "suggestedAnswer": { "@type": "Answer", "text": "
Solution:
Efficiency of Raj =
10020
= 5%
Work completed by Raj = 25%
Rest work = 75%
Efficiency of Abhijit =
7510
= 7.5%
Combined efficiency = 5 + 7.5 = 12.5%
They will complete the whole work by working together in,
=
10012.5
= 8 days ", "dateCreated": "7/24/2019 10:09:12 AM" } }