42 women can do a piece of work in 18 days, How many women would be required do the same work in 21 days.

  • 135
  • 236
  • 337
  • 438
Answer:- 1
Explanation:-

Solution:
Let X be the number of women required to finish the work in 21 days.
Now, using Work Equivalence Method:
42 × 18 = X × 21
X = 36.
Number of women required = 36.