A is thrice as good as workman as B and therefore is able to finish a job in 60 days less than B. Working together, they can do it in:

  • 120 days
  • 2
    2012
    days
  • 325 days
  • 430 days
Answer:- 1
Explanation:-

Solution:
RatiooftimestakenbyAandB = 1:3Thetimedifferenceis(3 - 1)2dayswhileBtake3daysandAtakes1day.Ifdifferenceoftimeis2days,Btakes3days.Ifdifferenceoftimeis60days,Btakes(32×60)=90daysSo,Atakes30daystodothework.A's1day'swork=130B's1day'swork=190(A + B)'s1day'swork=(130+190)=490=245AandBtogethercandotheworkin452=2212days

Post your Comments

Your comments will be displayed only after manual approval.

", "dateCreated": "7/24/2019 10:09:12 AM", "author": { "@type": "Person", "name": "Nitin Sir" } }, "suggestedAnswer": { "@type": "Answer", "text": "
Solution:
RatiooftimestakenbyAandB = 1:3Thetimedifferenceis(3 - 1)2dayswhileBtake3daysandAtakes1day.Ifdifferenceoftimeis2days,Btakes3days.Ifdifferenceoftimeis60days,Btakes(32×60)=90daysSo,Atakes30daystodothework.A's1day'swork=130B's1day'swork=190(A + B)'s1day'swork=(130+190)=490=245AandBtogethercandotheworkin452=2212days