3 men or 5 women can do a work in 12 days. How long will 6 men and 5 women take to finish the work ?

  • 120 days
  • 210 days
  • 34 days
  • 415 days
Answer:- 1
Explanation:-

Solution:
According to the question,
As they complete the same work in same time
6 men + 5 women
= 6 men + 3 men
= 9 men
If, 3 men does a work in 12 days
1 men does a work in 12 × 3
9 men does a work in
12×39
  = 4 days

Alternate :
3 men×12=5 women×12menwomen=53Total work=3×5×12=15×12=180 unitsEfficiency of 6 men+5 women=6×5+5×3=45Time taken by 6 men+5 women=18045=4 days

Post your Comments

Your comments will be displayed only after manual approval.

  = 4 days

Alternate :
3 men×12=5 women×12menwomen=53Total work=3×5×12=15×12=180 unitsEfficiency of 6 men+5 women=6×5+5×3=45Time taken by 6 men+5 women=18045=4 days
", "dateCreated": "7/24/2019 10:09:12 AM", "author": { "@type": "Person", "name": "Nitin Sir" } }, "suggestedAnswer": { "@type": "Answer", "text": "
Solution:
According to the question,
As they complete the same work in same time
6 men + 5 women
= 6 men + 3 men
= 9 men
If, 3 men does a work in 12 days
1 men does a work in 12 × 3
9 men does a work in
12×39
  = 4 days

Alternate :
3 men×12=5 women×12menwomen=53Total work=3×5×12=15×12=180 unitsEfficiency of 6 men+5 women=6×5+5×3=45Time taken by 6 men+5 women=18045=4 days
", "dateCreated": "7/24/2019 10:09:12 AM" } }