56 men can complete a piece of work in 24 days. In how many days can 42 men complete the same piece of work ?

  • 118
  • 232
  • 348
  • 498
Answer:- 1
Explanation:-

Solution:
Let the required number of days be x
Less men, More days (Indirect proportion)
42:56::24:x42×x=56×24x=(56×2442)x=32

Post your Comments

Your comments will be displayed only after manual approval.

", "dateCreated": "7/24/2019 10:09:12 AM", "author": { "@type": "Person", "name": "Nitin Sir" } }, "suggestedAnswer": { "@type": "Answer", "text": "
Solution:
Let the required number of days be x
Less men, More days (Indirect proportion)
42:56::24:x42×x=56×24x=(56×2442)x=32
", "dateCreated": "7/24/2019 10:09:12 AM" } }