Working 8 hours a day, 12 men can do a work in 30 days. Working 4 hours a day, 18 men can do work in ?

  • 130 days
  • 240 days
  • 345 days
  • 450 days
Answer:- 1
Explanation:-

Solution:
Let the required number of days be x
Less working hours, More days (Indirect Proportion)
More men, Less days (Indirect Proportion)
Working hours 4:8Men 18:12}::30:x

 4×18×x=8×12×30x=(8×12×30)(4×18)x=40