If 17 labourers can dig a ditch 20 m long in 18 days, working 8 hours a day; how many more labourers should be engaged to dig a similar ditch 39 m long in 6 days, each labourer working 9 hours a day ?

  • 134
  • 251
  • 368
  • 485
Answer:- 1
Explanation:-

Solution:
Let the total number of men to be engaged be x
More length, More labourers (Direct proportion)
Less days, More labourers (Indirect proportion)
Lentgh 26:39Days 6:18Hours per day 9:8}::17:x

 26×6×9×x=39×18×8×17x=(39×18×8×17)(26×6×9)x=68

∴ Number of more labourers = (68 -17) = 51

Post your Comments

Your comments will be displayed only after manual approval.


 26×6×9×x=39×18×8×17x=(39×18×8×17)(26×6×9)x=68

∴ Number of more labourers = (68 -17) = 51 ", "dateCreated": "7/24/2019 10:09:12 AM", "author": { "@type": "Person", "name": "Nitin Sir" } }, "suggestedAnswer": { "@type": "Answer", "text": "
Solution:
Let the total number of men to be engaged be x
More length, More labourers (Direct proportion)
Less days, More labourers (Indirect proportion)
Lentgh 26:39Days 6:18Hours per day 9:8}::17:x

 26×6×9×x=39×18×8×17x=(39×18×8×17)(26×6×9)x=68

∴ Number of more labourers = (68 -17) = 51 ", "dateCreated": "7/24/2019 10:09:12 AM" } }
Test
Classes
E-Book